2022 Annual Paving Project

Project Description

This project provides for improvements to ADA facilities and pavement preservation on Woods Creek Road from US 2 to Tjerne Pl SE. The anticipated work includes placement of fiber reinforced Hot Mix Asphalt (HMA), pavement repair, planing or grinding, construction of ADA ramps, pavement markings, utility adjustments, temporary traffic control and other associated work. In addition, this project includes updating pavement markings at other locations throughout the City.

Project Update

Construction started August 8th and ended in late September. Woods Creek Road (between US-2 and Tjerne Place SE) received a new surface of asphalt, upgraded sidewalk ramps and new striping. Lane line striping and pavement markings throughout the City was also completed.

Project Details

  • No. of road segments: 1
  • Quantity of paving: 590 tons
  • Paving area: 5,180 square-yards (SY)
  • No. of curb ramp improvements: 9
  • Design team: The Blueline Group
  • Construction contract: $606,430
  • Contractor: Lakeridge Paving Company 
  • Construction Management team: The Blueline Group

Project Timeline

BenchmarkDate
End constructionSeptember
PavingAugust 24th
Begin constructionAugust 8th
Pre-construction meetingEarly July
Award construction contractJune 28th
Bid OpenJune 14th
Advertise for contractor bidsMay 27th
Design phaseFebruary - May
Award Design contractFebruary 16th
Consultant InterviewsJanuary 12th, 2022
SOQ dueDecember 22nd
Issue RFQ for Design and CM ServicesDecember 6th, 2021
Project authorized by CouncilJanuary 25, 2022


Map of roads to be repaved in 2022

2022 Paving Map

2022 Road List

Road
Begin End
Woods Creek Rd US Hwy 2 Tjerne Pl
Madison St* W Elizabeth St W Main St
Powell St** S Kelsey St S Sams St

*Madison Street will be repaved under a separate contract. Click here for the project link.

**Powell Street will be repaved under a separate contract. Click here for the project link