Pavement grinding is planned for Tuesday, July 17th at the following locations: 159th Street SE (179th Ave to Park Ln), Powell Street (Park St to Kelsey St), Dennis Way (mid-block south to Main St), and Tester Road (Monroe High School south to corner). These roads are planned to be repaved on Thursday, July 19th.
Please expect alternating lane closures with flaggers and advance signage to direct vehicles through the work zones. Parking may be restricted in some locations. Residents may experience some inconvenience, including noise and delays. Access to homes and businesses will be maintained, with the exception of several hours immediately before and/or after paving. Emergency vehicle access will be provided, and arrangements will be made for garbage pickup and mail delivery whenever / wherever possible. Additionally, alternate walking routes will be made available.
We will continue to post construction updates, but you can always refer to the project website for updated information: http://www.monroewa.gov/628/2018-Pavement-Preservation