Woods Creek Road Water Main Replacement

Project Description

This project replaces approximately 750 feet of aging water main located under Woods Creek Road, between US 2 and Tjerne Place SE in 2021,  In 2022 this street segment will receive new asphalt surfacing and upgrade the sidewalk ramps to current federal standards.

  1. James Gardner

    Senior Engineer
    Phone: 360-863-4542

  2. Jammi Guion

    Construction Documentation Supervisor
    Phone: 360-863-4514

Project Timeline

Phase Start End
Design January, 2020 December, 2020
Construction April, 2021 June, 2021

Project Updates

July 29, 2021

Project has completed all connections to the new water main.  Waiting on concrete subcontractor to replace sidewalk and curbing removed as part of construction before trench can be permanently patched.  

June 28, 2021

Project proceeding on schedule.  Anticipate night work will begin on July 12.  

June 8, 2021

Contractor has put up message boards.  Work to begin Monday, June 14th.  Two way traffic to be maintained.  Work in the Tjerne/Woods Creek Road intersection to occur at night.  

May 27, 2021

Council awarded the project to Oceanside Construction on May 25th.   Contract documents are being compiles and a virtual pre-construction meeting is scheduled for 1PM on June 3rd.  The contractor is planning to start work on Monday, June 7, 2021.  Woods Creek Road will retain 2 lanes of traffic during construction, however there may be delays.  Businesses will remain open during construction.  Planned water shutdowns are scheduled to occur at night. 

May 13, 2021

The bids were opened on May 6, 2021.  After review, state licensing verification and reference calls, the lowest responsive bidder is Oceanside Construction Inc.  Council award is scheduled for May 25, 2021.  Anticipated start of construction is June 7, 2021.   There will be 2 lanes of traffic during construction.   Please adhere to flaggers directions or take alternate routes during construction.  Work is expected to be completed on or about July 30, 2021. 

April 29, 2021

Project is currently being advertised in the DJC.  Bids are to be opened on May 6, 2021.  Council award is scheduled for May 25, 2021.  Anticipate starting construction on June 14, 2021.    

March 29, 2021

City plans to advertise this project in early April.  Staff making final revisions to plans and specifications. 

February 28, 2021

Staff working on final Plans, Specifications and Estimate for the project.  Anticipate advertising construction in mid to late March.  

January 28, 2021

Design 100% drawings being worked on by staff.

December 30,2020

Design 90% drawings being worked on by staff.

November 30,2020

Design 90% drawings being worked on by staff. 

October 29,2020

Senior Engineer working on 60% design drawings.

September 29,2020

Senior Engineer working on 60% design drawings.

April 2020

Engineering staff have received the site topographic data from our on-call surveyor, and are working on the design. The design process will be ongoing throughout 2020.

Project Location Image

Woods Creek Water Main Project Image