Madison Sewer Separation

Project Description


This project will remove the storm water runoff from entering the sanitary sewer system by collecting, treating and infiltrating the runoff. It is proposed to use Filterra Systems to treat the runoff prior to infiltration and install permeable sidewalks to reduce the runoff to the infiltration basin. In conjunction with this work, the City will replace an old 4" water main and reconstruct the street to eliminate the excessive crown from past overlay projects.


Contact Us


  1. Jammi Guion


    Contracts Supervisor
    Email Public Works Contracts
    Phone: 360-863-4514

    Jim Gardner, PE 

    Project Manager
    Email Jim Gardner
    Phone: 425-754-1868

    Scott Peterson, PE

    Deputy City Engineer
    Email Scott Peterson
    Phone: 360-863-4606

The City is reaching out to the residents along North Madison for their input on the preferred layout for the Madison Combined Sewer Separation Project.  Staff has prepared a response method using SurveyMonkey to allow citizens to provide input.  Drawings  and survey access links are located below:

surveymonkey.com

public outreach drawings

The City will also send out postcards to owners and place informational hangers on resident doors by March 4th.  The survey will end and the above link will be removed on March 28th.  You input is important to us and the effort to respond is greatly appreciated.    

Project updates

Nov. 30, 2021

City Staff is working on design.  Construction to begin in Summer 2022

Oct. 28, 2021

City Staff is working on design.  Construction to begin in Summer 2022

Sept. 29, 2021

City Staff is working on design.  Construction to begin in Spring 2022

Sept. 1, 2021

City Staff is working on design.  Construction to begin in Spring 2022

July 29, 2021

City Staff working on design.  Construction to begin in Spring 2022

June 28, 2021

City Staff working on design.  Construction to begin in Spring 2022

May 26, 2021

City Staff has, after several meetings and discussions, review of citizen comments, review of survey results and verifying compliance with City Code come to the following design criteria.  The road will have 10-foot drive lanes and 8-foot parking lanes per City standards, the back of new sidewalks will remain at the same location as the back of the existing sidewalks, the City will pay the extra cost to install regular concrete for the sidewalks, the sidewalk along the east side of Madison from Main Street to the north side of the church property will extend to the new curb, bulb-outs will be redesigned so that no legal parking spaces are lost along the street, existing paths through the planter are will be replaced with concrete matching the existing width.  

April 26, 2021

City is still discussing Citizen comments and concerns before proceeding with the design.  

March 29, 2021

City held a public meeting with residents to discuss the project.  The on-line survey period has ended.  Staff is reviewing comments from the meeting and survey.  Waiting for Ecology approval of Design Report.  Will begin work on 90% drawings after completion of survey review.  

March 1, 2021

Staff posted survey monkey to this site for Citizen response.  

February 28, 2021

Staff is working on virtual open house for public comment.  Notices will be mailed to property owners and door hangers placed on residences and businesses to notify renters.  Look for these to come out in mid March.  

January 28, 2021

Staff reviewing design drawings.  Design Report submitted to Ecology for review.

December 30,2020

Staff is preparing for a virtual public review and comment, preparing suitable drawings and preparation of notifications of residents and property owners.  

November 30,2020

Design 60% drawings being worked on by staff.  Current schedule has project being advertised in May 2021.

October 29,2020

30% design drawings under review.  Current schedule has project being advertised in May 2021.

September 29,2020

Senior Engineer working on 30% design drawings.

August 27,2020

Project currently being designed.


Benchmark
Date
Apply for Grant
11/8/2016
Grant offered to City
4/23/2018
Comprehensive Plan Approved
6/13/2019
Council acceptance of Grant
8/27/2019
Project Authorization by Council
1/27/2020
Begin Project Design
1/28/2020
Covid Delays Begin
3/23/2020
Geotech Work Resumes
6/5/2020
Design completed
6/16/2021
Advertise for Construction
Summer 2021
Begin Construction
Summer 2021
Construction Complete
Fall 2021

Public Outreach Information

Madison Project Area