DOC Second Reservoir

Project Description

The City of Monroe 2015 Comprehensive Plan identifies the need for a second reservoir on the Department of Correction's (DOC) property to meet fire flow requirements. The new reservoir will be located near the existing 750,000 gallon reservoir and will be of similar size and height. 

The project consists of furnishing all labor, materials and equipment necessary for the construction of a new 850,000 gallon welded steel drinking water storage reservoir.  Related work includes water main connection to the existing 12-inch diameter water main, miscellaneous reservoir and site drainage piping improvements, reservoir overflow and drainage facilities, excavation, surface improvements, construction of two stormwater level spreaders , associated tank access road and structures, and related work.

Contact Us

  1. Jammi Guion


    Contracts Supervisor
    Email Public Works Contracts
    Phone: 360-863-4514

    Kim Klinkers, PE

    Project Manager
    Email Kim Klinkers
    Phone: 425-760-7895

    Scott Peterson, PE

    Deputy City Engineer
    Email Scott Peterson
    Phone: 360-863-4606


Project Updates

Re-advertisement for Contractor Bids (Nov 2020 - Dec 2020)

On November 19th and December 1st, this project will be re-advertised for contractor bids in the Daily Journal of Commerce. Refer to the Invitation to Bid for more information. The Engineer's probable cost opinion is $2,500,000. The bid open is scheduled for December 15th, 2020.

Advertisement for Contractor Bids  (Aug 2020 - Oct 2020)

The construction contract was advertised for contractor bids in the Daily Journal of Commerce on August 25, September 1, and September 15, 2020.  The Engineer’s probable cost opinion was $3,200,000.  Four bids were received and opened on September 23, 2020, with bids ranging from $2,339,020 to $2,497,232. 

After the bid opening, one bidder submitted a protest to the award process, expressing concern over the validity of supplemental bidder criteria found in the instructions to bidders and the corresponding validity of one of the other bids. City staff evaluated the protest, including the potential delay and additional cost that would be incurred in resolving the issue, and determined the most expedient and cost-effective course of action will be to reject all bids. The project will be rebid with clarified information for the bidder criteria.

Design & Permitting  (May 2019 - Aug 2020)

City Staff began planning for the design phase by soliciting engineering services in May 2019. Four firms responded to the advertisement. Murraysmith, Inc. was determined to be the most qualified firm to perform the design work for this project. The design contract includes topographic surveying, geotechnical engineering, civil engineering, and structural engineering, in addition to bidding support services.

Project Timeline

Key Benchmark Date
Authorize Project by City Council January 22, 2019
Advertise for Design RFP May 2019
Begin Design Phase June 2019
End Design Phase June 2020
Advertise for Contractor Bids August 25, 2020
Bid Open September 23, 2020
Bids rejected by City Council October 27, 2020
Re-advertise for Contractor Bids November 19, 2020
Bid Open December 15, 2020
Award Contract by City Council January 12, 2021
Begin Construction February 2021
Construction Complete December 2021
DOC Aerial