Adams Lane Utility Replacement

Project Description

This project replaces approximately 630 feet of aging water main and approximately 400 feet of aging sanitary sewer main. This work will be done within that portion of Adams Lane, beginning at the intersection of Adams Lane and Pike Street and ending in the alleyway approximately 500 feet to the north. Properties that have service connections within the project area will have new water service lines and meters, as well as new side sewer connections.

The contract allows for 35 working days to complete the project. Adjustments may be made to the time if weather events interfere with the planned work. We anticipate the project to be completed near the end of May, 2020.

For more information, please contact the project manager:
Jim Gardner, PE
(360) 863-4542
Email Jim Gardner

Project Update

2/26/2020 - The project is scheduled to begin construction on March 23rd, 2020. Rodarte Construction Inc is the contractor who successfully submitted the lowest bid to perform the work. After mobilizing to the jobsite, the contractor’s first effort will be to install a temporary water supply for adjacent properties. This will provide for water service while the contractor installs the new water main. 

Project Timeline

Benchmark Date
Project Authorization by Council January 8th, 2019
Begin Project Design January 9th, 2019
Design Completed December 31, 2019
Bid Advertisement January, 2020
Begin Construction March, 2020
Construction is Completed May, 2020
Vicinity Map