- Home
- Government
- Departments
- Public Works
- Design & Construction
- Projects
- Chain Lake Road Shared Path Extension
Chain Lake Road Shared Path Extension
Project Description
The City of Monroe received a federal grant through Puget Sound Regional Council (PSRC) to design and purchase additional right-of-way for extending the shared sidewalk/path north along Chain Lake Road and end at Brown Road. The sidewalk would match to the existing sidewalk in the vicinity of Rainier View Road.
Schedule
Date | Description |
---|---|
2017 - 2018 | Design Process |
2018 | Right-of Way Acquisition |
2019 | Design/Right-of-Way Complete |
2021 | Construction Begins |
no timeline | Construction Completion |
Project Updates
August 29, 2022
Project is complete and open to the public as of 8-2-2022. City staff working on project closeout documents.
July 28, 2022
A section of sidewalk has heaved and needs to be replaced. Contractor is working to get subcontractor out to replace heaved section. All other work has been completed.
June 28, 2022
Contractor mobilized back onto the site on June 21, 2022. Erosion Control items have been removed and contract work has begun.
May 30, 2022
Project still in suspension until suitable weather arrives. Anticipate resumption of work in mid-June, 2022
April 28, 2022
Project still in suspension until suitable weather arrives. Anticipate resumption of work in May, 2022
March 30, 2022
Project still in suspension until weather improves. Anticipate work resuming in May, 2022.
Feb 28, 2022
City suspended the project until the weather improves. Anticipate work resuming in April, 2022
Jan. 31, 2022
City has suspended construction until the weather improves. Anticipate resumption of work in April.
Jan. 4, 2022
City will suspend the project once all the sidewalk has been poured and all the driveways paved.
Nov. 30, 2021
City has suspended top soil placement and hydroseeding until the weather is suitable for planting. Contractor has completed the wall and is preparing the subgrade along the wall for concrete placement.
Oct. 28, 2021
Contractor is placing top soil. Most of the trail is complete, however there is a portion that requires a wall that has been delayed due to material unavailability. Once the wall is finished, the trail can be completed and opened to the public for use.
Sept. 29, 2021
Contractor has started pouring the concrete for the trail. Project scheduled for completion by the end of the month.
Sept. 1, 2021
Contractor will have subgrade ready early next week. He will then proceed with the storm system installation followed by installation of the trail surfacing.
Aug 19, 2021
Project is moving slowly due to multiple utility conflicts and clearing issues. Excavation work is almost completed and the next phase will be to install the drainage system along the trail.
July 29, 2021
Contractor began work on July 12, 2021. Working on CO for removal of unidentified trees that need to be removed. Clearing should be completed by August 6, 2021.
June 28, 2021
Project delayed until July 6 due to permit issues.
June 8, 2021
Contractor is not ready to begin work on June 14th. Hopes to start on June 21st or 28th.
May 26, 2021
City Council award the contract to SRV Construction on May 25, 2021. Anticipated start of construction is June 14, 2021. Expect traffic delays and one-lane road during construction. Please adhere to flaggers directions or take alternate routes during construction. Work is expected to be completed on or about September 10, 2021.
City Staff put out a request for qualifications for a Construction Management firm to manage the construction project. There were three respondents. Interviews were held and Perteet was chosen as the best qualified for this project. Council is scheduled to award the Construction Management contract to Perteet on June 8, 2021.
May 13, 2021
The bids were opened on May 6, 2021. After review, state licensing verification and reference calls, the lowest responsive bidder is SRV Construction Inc. Council award is scheduled for May 25, 2021. Anticipated start of construction is June 14, 2021. Expect traffic delays and one-lane road during construction. Please adhere to flaggers directions or take alternate routes during construction. Work is expected to be completed on or about September 10, 2021.
May 6, 2021
Low apparent bidder was SRV Construction. City is in the processes of selecting a firm to provide Construction Management for the project. Council scheduled to award contracts to SRV on May 25, 2021. Council scheduled to award Construction Management contract on June 8, 2021. Anticipate construction starting June 14, 2021.
March 31, 2021
City began advertising the project for construction bids effective March 31, 2021. All bids must be submitted to the City before 11:00AM on April 22, 2021. Please reference Status above if you are interested in bidding on the project.
March 29, 2021
City will be advertising this project for construction soon. Chain Lake Road will see traffic lane closures during the construction period. More will be known once the contractor is known.
February 28, 2021
City will be ready to advertise the project middle to late March.
January 28, 2021
Right-of-Way Consultant negotiating Temporary Construction Easement extensions.
December 30,2020
Project has been authorized for construction. Advertisement for bids is scheduled to go out in mid February.
November 30,2020
ROW purchase documents have been sent to WSDOT for review and approval. Draft construction obligation documents have been sent to WSDOT Local Programs for review and comment.
October 29,2020
Plans, Specifications and Estimate are complete. Preparing ROW purchase documents for certification of ROW.
September 29,2020
Last of Right-of-Way purchases have been sent to the title company for recording.
August 5,2020
Right-of-Way negotiations are complete and purchases are being processed. Designer is finalizing plans for bid in early 2021. Construction expected to begin in Spring of 2021.
July 17,2020
Final design is being worked on. Meanwhile, the City is negotiating property rights with adjacent property owners. The Right-of-Way acquisition process is anticipated to take the remainder of the year. Construction is slated for 2020.
April 1,2020
The design has reached 90% completion status and is being reviewed be engineering staff.
February 13,2020
The design is being advanced toward 90% completion. Meanwhile, property valuations and negotiations are underway to acquire the necessary right-of-way for this shared path.
October 15, 2018
The project design phase is at 60% complete. Staff continue to coordinate with the design consultant and property acquisition consultant as this project moves forward.
August 10,2018
Design efforts are ongoing, as well as efforts to acquire additional right-of-way from adjacent properties.
January 28,2018
The City awarded the design contract to WH Pacific. This firm has begun the design process.
September 8,2017
Engineering staff are working with WSDOT to clear the project for advertisement to seek the services of a design consultant.
August 2,2017
Engineering staff submitted documents to WSDOT to request obligation (release) of design funds. Once obligation has been obtained, the City will seek the services of an engineering consultant to begin the design of this sidewalk extension.
May 1,2017
The project is funded by a federal grant, which is administered by WSDOT. The City will seek the services of a design consultant once WSDOT authorizes us to begin project expending.
February 3,2017
We will advertise for a design consultant in the spring this year.
CONTACT US
Jammi Guion
Contracts Supervisor
Phone: 360-863-4514
Jim Gardner, PE
Project Manager
Phone: 425-754-1868
Scott Peterson, PE
Deputy City Engineer
Phone: 360-863-4606
Listens