- Home
- Government
- Departments
- Public Works
- Design & Construction
- Projects
- 177th Ave Sewer Line Replacement
Create a Website Account - Manage notification subscriptions, save form progress and more.
The existing 10" concrete sewer line along 177th Ave has inadequate capacity for peak flow conditions. This deficiency was identified in the 2015 Utilities System Plan and identified operationally during storm events. A proposed 16" pvc line will be installed along 177th Ave to Main Street where it will connect to the West Main Pump Station Force Main and continue east and terminate at the Park Place Pump Station.
RH2 Engineers were selected to perform the design effort for this project. Construction is expected in the Spring of 2023 with the completion expected by the Fall 2023.
Budget | Contract | |
Design | $140,485 | |
Construction | ||
Total | $959,960 |
June 2022 - Select and execute consultant agreement with RH2 for engineering services
January 2023 - Review 50% drawings
Milestone | Date |
---|---|
Design Complete | February 2023 |
Project Bid | April 2023 |
Bid Award | May 2023 |
Notice to Proceed | May 2023 |
Construction Begin | June 2023 |
Construction Complete | October 2023 |
Contact Us
Jammi Guion, Project Coordinator
jguion@monroewa.gov or 360-863-4514
John Lande, Project Manager
jlande@monroewa.gov or 360-863-4550
Listens