177th Ave Sewer Line Replacement

Project description

The existing 10" concrete sewer line along 177th Ave has inadequate capacity for peak flow conditions.  This deficiency was identified in the 2015 Utilities System Plan and identified operationally during storm events.  A proposed 16" pvc line will be installed along 177th Ave to Main Street where it will connect to the West Main Pump Station Force Main and continue east and terminate at the Park Place Pump Station.

RH2 Engineers were selected to perform the design effort for this project.  Construction is expected in the Spring of 2023 with the completion expected by the Fall 2023.


BudgetContract
Design
$140,485
Construction

Total$959,960


Project Updates

June 2022 - Select and execute consultant agreement with RH2 for engineering services

January 2023 - Review 50% drawings



Milestone Date
Design Complete February 2023
Project Bid April 2023
Bid Award May 2023
Notice to Proceed May 2023
Construction Begin June 2023
Construction Complete October 2023
177th Sewer

Contact Us

Jammi Guion, Project Coordinator

jguion@monroewa.gov   or 360-863-4514


John Lande, Project Manager

jlande@monroewa.gov   or 360-863-4550