Smith St.& Park St. Utilities Upgrade Project

 




Project Description

The aging water main will be replaced in Smith Street and a portion of Park Street. Additionally, the sewer main in Smith Street will be upgraded to increase functionality. The project design documents will be prepared in 2017, with actual construction occurring the following year in 2018.


  Aerial VicMap.PNG
 Schedule
2017 Design Process
Jan. 2018
Advertise for Construction
Feb 2018 Contract Award to Construction Contractor
March 2018 Construction Begins
July 2018 Construction Completion
 Status
Project is under design development.
Project Updates
For more information contact:
Jim Gardner, PE  
360-863-4542
Email

Project Updates
2/3/17 - A topographic survey is underway for this project. This data will provide the background information necessary to begin the utility designs.