Air Field Water Main Upgrade Project

 




Project Description

The City is developing plans to increase the size of the water main adjacent to First Air Field (Monroe airport). The objective is to increase water supply to the Foothills area during peak demand or emergencies. Design will occur during 2017 with actual construction commencing in the spring of 2018.


  Aerial VicMap.PNG
 Schedule
2017 Design Process
Feb. 2018 Advertise for Construction
Feb. 2018 Contract Award to Construction Contractor
March 2018 Construction Begins
June 2018 Construction Completion
 Status
Project is beginning the design process.
Project Updates
For more information contact:
Kim Klinkers, PE  
360-863-4531
Email

Project Updates
2/3/17 - A topographic survey of the project area is underway. This will provide background information to design with.